EverOn Data Center Services President and CEO Tom Mertz is featured in a new Buildermuse Q&A about data center growth and what it asks of the companies building critical digital infrastructure.

In the interview, Tom Mertz talks about the growth that took EverOn’s construction business from $87 million in revenue in 2021 to nearly $1.7 billion in 2025. That growth led to the launch of EverOn Data Center Services as an independent data center builder.

Mertz also covers three of the industry’s biggest challenges:

  • Equipment lead times: Generators, switchgear, transformers and chillers can take 12 months to two years to arrive.
  • Project schedules: Bringing utility power to a 50- to 100-megawatt data center campus can take eight to 12 months.
  • Liquid cooling: New cooling technologies are changing construction requirements, commissioning and what’s asked of specialized trade partners.

In the full Q&A, Mertz explains how EverOn approaches these challenges on projects across the country.